Skip to main content
Menu

E Branch Track and Intersection Upgrades 64% Complete

Updated on August 20, 2021

From August 2 to August 29, crews are working 24 hours a day, seven days a week to upgrade infrastructure on the E Branch.

Learn more about the Green Line Track and Intersection Upgrades

Work We’ve Completed

Over the last 17 days, we have:

  • Completed 90% of the planned track replacement along Huntington Ave
  • Improved five pedestrian crossings
  • Started work on the Tremont Street/Francis Street intersection

Overall, crews have now completed 64% of the track and intersection upgrades on the E Branch.

Upcoming Work

Accelerated work on the E Branch will continue through August 29. In addition to the project’s planned improvements, crews will use this period of full access to upgrade five more pedestrian crossings and renew 600 additional feet of track.

During this work, the 39 bus will not collect fare from riders boarding between Heath Street and Brigham Circle (August 2 – 29) and between Heath Street and Northeastern University (August 24 – 26).

Check Green Line E service alerts

For More Information

Get project news, updates, and information delivered to your inbox.

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects