MBTA Makes Further Progress on Expedited Critical Track Work on Orange Line, Removes Seven Speed Restrictions

Posted on March 25, 2024

Four speed restrictions also removed on the Red Line last week.

Crews performed track work in the underground tunnel of the Orange Line. Complimentary photo by the MBTA Customer and Employee Experience Department.
Crews performed track work in the underground tunnel of the Orange Line. Complimentary photo by the MBTA Customer and Employee Experience Department.

The MBTA today announced the completion of critical track work on the Orange Line. Crews accomplished this critical work due to unencumbered access to track areas while Orange Line service was suspended between Jackson Square and North Station for four days from March 18-21. As a result, six safety-related speed restrictions were removed last week with a seventh removed over the weekend following final completion work.

“With each step, we are following through on our commitment to rebuild our tracks to give our riders the improved reliable trip they deserve. I’m proud of the dedicated workforce that worked in a short window of time while delivering on significant work along the Orange Line corridor,” said MBTA General Manager and CEO Phillip Eng. “There is much more to do, and we are determined to make tough decisions to prioritize work while balancing the need to ensure the public has sufficient options to use mass transportation alternatives. We thank riders for their patience and understanding as we continue reinvesting in our infrastructure and make important progress to give them a system that they can rely on and be proud of.” 

Infrastructure improvements were accomplished along the Orange Line. Complimentary photo by the MBTA Customer and Employee Experience Department.
Infrastructure improvements were accomplished along the Orange Line. Complimentary photo by the MBTA Customer and Employee Experience Department.

The important work accomplished on the Orange Line means riders will experience a more reliable trip with fewer unplanned service disruptions related to older tracks, older infrastructure, signal issues, or power problems. Riders will also be provided with a safer ride as a result of this state of good repair work. 

Crews worked in critical track areas during this Orange Line diversion. Complimentary photo by the MBTA Customer and Employee Experience Department.
Crews worked in critical track areas during this Orange Line diversion. Complimentary photo by the MBTA Customer and Employee Experience Department.

With unencumbered access to Orange Line stations, crews were able to accomplish critical work and maximize access to tracks and stations in a number of ways:

  • More than 5,000 feet of rail was installed.
  • 27 cologne egg rail fasteners were replaced.
  • 63 rail “shoulders” were cored. 
  • Nearly 260 plates were installed.
  • 10 switch timbers embedded in concrete were replaced by the Maintenance of Way team.
  • 500 feet of stringer cable was replaced.
  • Nine third rail insulators were replaced by the Maintenance of Way team.
  • Critical switch and crossover work was accomplished.
  • Tunnel inspections were performed between State and Haymarket.
  • Structural overhead inspections of stations were accomplished at Chinatown, Massachusetts Avenue, Ruggles, and Roxbury Crossing with additional station entrance inspections performed.
  • Concrete slab sections were replaced within the State station “Rainbow Corridor.”
  • Station inspections were accomplished between Jackson Square and Downtown Crossing.
  • Modernization work along the southwest corridor between Roxbury Crossing and Chinatown was performed with concrete coring accomplished in eight locations. 
  • Security and emergency management enhancements were performed at Downtown Crossing.
  • Crews performed visual surveys and measurements of tunnels, communication rooms, and emergency exits from Ruggles to State in support of the MBTA’s Statewide Radio System cable installation path. Crews also surveyed Station Communication rooms and public areas for radio equipment installations as the crew progressed from station to station through the tunnels.
Security and emergency management enhancements were performed at Downtown Crossing. Complimentary photo by the MBTA Customer and Employee Experience Department.
Security and emergency management enhancements were performed at Downtown Crossing. Complimentary photo by the MBTA Customer and Employee Experience Department.

As a result of this critical work, the following safety-related speed restrictions are no longer in place:

Speed Restriction NumberRestriction Information and LocationStatus
Speed Restriction Number

1.    526479

Restriction Information and Location

Northbound between Ruggles and Massachusetts Avenue

Status

Removed

Speed Restriction Number

2.    000045

Restriction Information and Location

 Northbound at Back Bay 

Status

Removed

Speed Restriction Number

3.    523874

Restriction Information and Location

Northbound between Back Bay and Tufts Medical Center 

Status

Removed

Speed Restriction Number

4.    523882 

Restriction Information and Location

Northbound between Tufts Medical Center and Chinatown

Status

Removed

Speed Restriction Number

5.    000055

Restriction Information and Location

Southbound at Chinatown

Status

Removed

Speed Restriction Number

6.    000061

Restriction Information and Location

Northbound at Back Bay

Status

Removed

Speed Restriction Number

7.    000002

Restriction Information and LocationNorthbound between Tufts Medical Center and ChinatownStatusRemoved

Additionally, four speed restrictions were removed on the Red Line last week:

Speed Restriction NumberRestriction Information and LocationStatus
Speed Restriction Number1.    000128Restriction Information and LocationBetween Quincy Center and Quincy AdamsStatusRemoved
Speed Restriction Number2.    000132Restriction Information and LocationBetween Andrew and JFK/UMassStatusRemoved
Speed Restriction Number3.    000129Restriction Information and LocationBetween North Quincy and WollastonStatusRemoved
Speed Restriction Number4.    000131Restriction Information and Location Between JFK/UMass and North QuincyStatusRemoved


A variety of other in-station work also took place along the Orange Line to further enhance the rider experience, including: 

  • cleaning, sanding, and painting wooden station benches; 
  • fire retardant installations; 
  • station painting;
  • door repairs;
  • yellow tactile edging repairs to platforms; 
  • flooring repairs to prevent tripping hazards; 
  • concrete repairs; 
  • stairway upgrades and repairs, including handrail repairs; 
  • waste receptacle replacements; 
  • powerwashing and cleaning work; and
  • installing/replacing station signage, including system maps.